1.Electrification, construction, testing and commissioning of 2 depositors / receivers in the lignite yard of Ptolemaida V substation (TERNA, 4358 sub 010, 2021)
2.Design, supply, transport, installation and commissioning of a V60 steam power unit with a combined capacity of 660mwel, with powdered lignite fuel, and with the possibility of providing a thermal power of 140mwth for district heating. Diesel & auxiliary steam electrical installations. (TERNA, 4311-sub-324, 2020).
3.Design, supply, transport, installation and commissioning of a V60 steam power unit with a combined capacity of 660mwel, with powdered lignite fuel, and with the possibility of providing a thermal power of 140mwth for district heating. Electrical installations in buildings (KT 9-10, KT11-17, KT 13-14), (TERNA, 4311-sub-283, 2019-2020)
4.Design, supply, transport, installation and commissioning of a steam power unit V with a combined capacity of 660mwel, with powdered lignite fuel and with the possibility of providing a thermal power of 140mwth for district heating. Electrical installations in the building KT6A., (TERNA, 4311-sub-114, 2017-2019)
5.Electromechanical works at the 13 airports of FRAPORT (SPPAL, 2018-2021) electromechanical upgrade of a barren land mine in the main field of LKDM (contract P340016026 – ER2, 2017).
6.Installation of electrical equipment in the waste management unit of Western Macedonia (SDΙΤ, HERHOF GMBH, COMPOSTING PLANT WESTERN MACEDONIA, 2016-2017).
7.Installation of UPS devices and their wiring at the Syntagma station of Attiko Metro (ELKOM, 2015-2017).
8.Installation of low voltage metering system for large customers (contract G02/13/0189, 2014-2015).
9.Provision of specialized technical support and maintenance services for high – ultra – high and medium voltage equipment of unit II of the Kardia substation (2014).
10.Design, supply and installation of equipment for the construction, operation and maintenance of a computer room and related infrastructure in the IPTO headquarters. Electrical work (contract 536/2014, 2014).
11.Repair of automatic coupling system of compensating capacitors NoI in the substation 150/20 Kv (contract 112. ΛΚΝ-0077, 2014).
12.Electrical construction of substations and conveyor equipment of the southern field mine / sector 7 of the lignite center of Western Macedonia (DMAOR contract 157, 2013-2014).
13.Maintenance of electrical equipment “ENGINE BEARING” MON. I MES Melitis (contract of AIS Μ 6728.2012.029, 2012).
14.Replacement of medium voltage fields 20kv and 6kv in the substations and film stations of the mine of the southern lignite center of Western Macedonia (DMAOR contract 134, 2011-2012).
15.Electrical construction of equipment along conveyor belts K5, K6 and conversion of T / D 2 from 1200mm to 1800mm (contract 2011.111/ΛΚΔΜ, 2011).
16.Electrical works for the displacement of T / D13B and the head T / D3 of KOPA (contract 2011.122 / LKDM, 2011).
17.Supply and installation of electrical equipment for the operation of the BY-PASS SILO gypsum conveyor (HVAC contract Μ6728.2011.033, 2011).
18.Electrical head erection type B = 2400 (contract 2011.125/ΛΚΔΜ, 2011).
19.Electromechanical construction of four (4) conveyor supply stations for the conveyor belts of the Mavropigi mine of DEI(contract P341110026-ER, 2011).
20.Electromechanical construction of four (4) modified converter stations with frequency converters, for conveyor belts of the Mavropigi mine of DEI(contract P341111017-ER, 2011).
21.Electrical construction of conveyor equipment K3, K4 lignite interconnection of KOMANOS settlement – Kardias substation and T / D 7C branch extension E7 (contract 2010.185 / LKDM, 2011).
22.Modernization of the electrical part of four machines (two receivers and two depositors) in the lignite center of Megalopolis (DMAOR contract 73, 2010-2011).
23.Reconstruction of electrical equipment T / D K2 and T / D K3 of Amyntaio mine (contract 2009.157 / LKDM, 2009-2011).
24.Dismantling of 17-7A conveyor electrical equipment, their transfer to new locations and their relocation (contract 2010.303 / LKDM, 2010).
25.Electrical construction of conveyor equipment L3 and CSF works length of T / D L4 and L5 (contract 2010.151 / LKDM, 2010).
26.Electrical works along the conveyors for the needs of the reconstruction of the A7 deposit sector (contract 2010.162 / LKDM, 2010).
27.Electrical construction of cables after their terminals on the conveyor belts of sub-branch E7 of the southern field of LKDM (DMAOR contract 12108, 2010).
28.Removal and repositioning of cables from the support bearing of the receiving tape of the depositor A2 (contract 2010.364 / LKDM, 2010).
29.Removal and replacement of cables of the E4 excavator, from the support bearing arm No2 and from Balauro (contract 2009.601 / LKDM, 2009).
30.Electrical works in the lignite interconnection sector ONP and OPK (contract 2009.082 / LKDM, 2009).
31.Supervision, inspection, maintenance and repair of internal electrical installations and moving installations of the Aliveri metal structures ladder (DMAOR 125 contract, 2008).
32.Supporting electrical works in the field of maintenance of the Kardia PPC (contract of the PPC. Κ. S-7104, 2008-2009).
33.Removal and repositioning of cables from the support bearing of the deposition arm of the tape No. 2 of E5 (contract 2008.142 / LKDM, 2008).
34.Electrical construction of conveyor belts and mining substations of the lignite center of Western Macedonia (DMAOR contract 120, 2007-2010).
35.Electrical construction of mining conveyors in the center of Western Macedonia (DMAOR contract 60, 2005-2006).
36.Electrical construction of lignite transport conveyors (K5, K6, K7) and the external deposition branch of deposit A7 (conveyor 133A, 143, 153) of the southern field mine (DMAOR contract 5248728, 2004).
37.Dismantling of cables and electrical equipment along conveyor belts 153, 133A, 131, 133 and 122 (DMAOR contract 5246718, 2004).
38.Electrical construction of Mavropigi mine conveyor belts (DMAOR contract 22, 2003-2004).