UPGRADING WORKS FOR A TOTAL OF 15 COSMOTE MSC BUILDINGS AND 5 DATA CENTERS OF IPME, WHICH INCLUDED THE FOLLOWING:

DEMOLITION OF EXISTING NETWORKS AND ISOLATION WORKS
MASONRY CLEANINGS – TECHNICAL SPACES
INSTALLATION OF EPOXY FLOORS
INSTALLATION OF REFRACTORY PARTITIONS, GLASSES AND FIRE SAFETY DOORS
INSTALLATION OF FIRE BARRIERS IN ELECTRICAL PASSES WITH FIRE PROTECTION INDEX F90
INSTALLATION OF NEW FLOORS (TILES, VINYLS, ANTISTATICS)
INSTALLATION OF ROOFED FLOORS
INSTALLATION OF FALSE MINERAL FIBER
FRAME INSTALLATIONS (ALUMINUM, SYNTHETIC)
INSTALLATION OF INSULATIONS
1. Supply of prefabricated reinforced concrete sleepers for the installation of rails and conveyors in the lignite yard (ΤΕRΝΑ, 4358 sub 003, 2020).

2. Design and construction of 2 depositors / receivers on rails after the collaborating folders and T / D for the lignite yard in unit V of Ptolemaida substation (ΤΕRΝΑ 4358 sub 007, 2020)

3. Manufacture of counterweights for depositor / receiver machines in unit V of Ptolemaida substation (ΤΕRΝΑ 4358 sub 008, 2020)

4. Construction of a retaining wall in T / D L1 and L3 of OPKA and construction of a base for a metal road bridge (contract 2017.206 / LKDM, 2017).

5. Construction of an A4 building at the Ptolemaida substation for the housing of the central machine shop LKDM (contract 2016.227 / LKDM, 2017).

6. Reconstruction of building A5 in the Ptolemaida substation for the housing of the central machine shop LKDM (contract 2016.228 / LKDM, 2017).

7. New branch of Ag. Dimitriou substation ash collection conveyors, width B = 1800mm in LKDM (contract DMAOR contract – 163 / 5258643, 2015-2016).

8. Construction of fencing in the pump shop K.O.PA. and at the K.O.P.K. (contract 2014.218 / LKDM, 2015).

9. Construction and reconstruction of fences at Agios Dimitrios substation (contract 6300003385, 2015).

10. electromechanical and construction projects for the upgrade of Chalandri, Ampelokipi, Chain and Acropolis fields (contract 292/2015, 2015).

11. Reconstruction and construction of a promotional head width B = 1800mm in the complex of the Kardia mine (DMAOR contract – 162 / 5246621, 2014-2015).

12. Configuration of aerial workshop space and vestibules – canopies of electrical technician K.OP.Ka. (Contract 2014.209 / LKDM, 2014-2015).

13. Construction of fences for the security of LKDM facilities (contract 2014.203 / LKDM 2014-2015).

14. Design, supply and installation of equipment for the construction, operation and maintenance of a computer room and related infrastructure in the IPTO headquarters. Construction projects (contract 282/2014, 2014).

15. Design, supply and installation of equipment for the construction, operation and maintenance of a computer room and related infrastructure in the IPTO headquarters. Electrical project (contract 536/2014, 2014).

16. Dismantling – transport and construction along conveyor equipment for the new S. Pedio mine junction section 1 (1st phase) (DMAOR contract – 154/5228619, 2013-2014).

17. Construction and erection of conveyor equipment B = 2400mm for the new mine junction of S. Pedio sector 7 (DMAOR contract – 150/5226610, 2013-2014).

18. Relocations, improvements, modernizations of KOPK buildings. (Contract 2012.118 / LKDM, 2012-2013).

19. Reconstruction of node section 5 of the mine of southern Pedio (Phase A). Interconnection of overhead excavators with the lignite complex. 2. Construction works on the lignite interconnection conveyors from the Kardias mine to the southern field mine (contract DMAOR-142/5208619, 2010).